PROJECT OVERVIEW
The Raftsundet
Bridge with a main span of 298m and a total length of 711m, was
the longest concrete cantilevered span in the world when the
cantilevers were joined at June 24th 1998. The bridge
was opened for traffic at November the 6th the same
year. The structure is exposed to a severe wind climate with a
design gust wind speed of almost 60 m/s. The surrounding alpine
topography with high mountains raising up to 1000m above sea
level, creates fluctuating wind forces of large magnitude on the
bridge. The dynamic wind climate severely affects the slender
columns and the bridge beam. The main span is constructed in
high strength lightweight aggregate (LWA) concrete LC60 and the
side spans and piers in normal density (ND) concrete C65. The
bridge is high level, providing a ship channel of 45 x 180 m.
Raftsundet
Bridge is a part of the ferry free mainland connection for the
Lofoten islands. The Lofoten islands are located north of the
Arctic Circle in the county of Nordland in Northern Norway.
Owner: Public Roads
Administration, Nordland (PRAN)
Contractor: AS Anlegg
Architects: BOARCH A/S
Designer (EOR):
Aas-Jakobsen (Information on this page kindly provided by
them)
Key data
Time Schedule:
Contract award, design: 1995
Contract award, construction: 1996
Construction completed in 1998
Cost (1996):
Tender price
(1996): US$14.3 mill
Total project cost (1996) US$16.2 mill
Materials:
-
LWA-concrete
in main span: LC60
-
ND-concrete
in side spans and piers: C65
-
Tendons: 140
mm2 strands S0.2=2800–3300 kN
Geometry:
Spans:
86+202+298+125= 711 m
Width overall: 10.30 m
Ship Channel: H x W = 45 x 180 m
Design considerations
In 1991 PRAN
arranged an architectural competition to find the most favorable
bridge design for this particular location. The competition was
open for all kinds of bridge types, but the topography and the
actual range of span lengths favored a concrete cantilevered
bridge or a cable stayed bridge. Several bridge designs were
proposed, notably with cantilevered or cable stayed bridges. The
jury decided that a concrete cantilevered bridge proposed by
Aas-Jakobsen A/S with a continuous horizontal curve best could
fit into the local topography. Cost estimates of the two bridge
types clearly favored the concrete cantilevered bridge, which
was then chosen by PRAN for construction.
The structure
is fully continuous, with flexible twin piers and large
foundations to solid rock on dry land. Expansion joints are
provided at each abutment. Compared to a design with ND-concrete
C65 in the main span, the savings were in the order of US$ 0.4
mill. Auxiliary piers were required to stabilize the
free-standing pier/balanced cantilevers during construction.
Construction methods
The following
construction methods were a basis for the detailed design:
Wind climate
investigations
Because of the
severe wind climate at the bridge site, wind measurements were
necessary to establish reliable design parameters to describe
the dynamic wind field. Dr.Ing. A. Aas-Jakobsen AS was engaged
by PRAN to plan and perform the detailed wind measurements
including evaluation of the dynamic wind parameters to be used
in the detailed design of the bridge. Three independent wind
sensors were mounted on a 30m high mast at different levels. The
wind-sensors consist of three-axial propellers measuring the
momentary wind velocity in three orthogonal directions in space
simultaneously. The data were recorded 5 times every second for
mean wind speeds higher than 10m/s.

Click on picture for overview.
|